Posts Tagged ‘round pole timber construction’

More work on the back roof

Saturday, May 12th, 2012

With the sudden advent of summer, we’ve been moving rapidly ahead on the rear roof. Three days of solid work has seen

  • the roof lights installed
  • the two membranes laid
  • flashing around 8 of the 10 light frames completed (we ran out of flashing tape and none of the local builders merchants have any more in stock right now)
  • the finishing work done to close the gap at the rear gully
  • the last leg to support the purlins installed
  • the rear land drain laid
  • the gravel infill completed

PET soft drink bottle lights

(more…)

Slow your roll

Tuesday, April 17th, 2012

There is a saying about building. There is ‘good’, there is ‘fast’ and there is ‘inexpensive’. You can have any two.

This time last year I hired a local team of builders to put up a balcony and trellis on the main building, finish the schist facing stone on the log store, and re-roof the small building. I knew their work – many foreigners locally have had them turn schist animal houses into habitable structures – and it’s generally reasonable enough for the price, though you get what you pay for. I figured if I didn’t throw too many unfamiliar techniques and materials into the mix they couldn’t go wrong with a simple wooden structure. The main rationale was that they had ready access to the sizeable amount of chestnut timber which was needed to construct the balcony, and which we were struggling to lay our hands on, but in truth I was also succumbing to the frustrations of slow progress.

Finished balcony and trellis

(more…)

Room at the back

Saturday, April 7th, 2012

Work has been steadily progressing on the waterproofing-the-back-of-the-main-building project started back in January.

Rear of main building

(more…)

Of winter heat and summer cold

Thursday, January 12th, 2012

With all the clearing work we’ve been doing in the woods, there’s now a need to get all the firewood-to-be under cover to season well before use. The log store we’ve been constructing next to the main building at last has its roof – a patio area – complete. We just need to relocate the things presently occupying it – like the washing machine – which, as is the way of these things, ideally requires completion of another couple of stages in the project beforehand.

Log store patio roof under construction

Log store patio roof under construction – membrane goes down on screeded roof

(more…)

Roofed

Saturday, December 31st, 2011

In a coincidental but fitting end to 2011, we’ve been finishing up several jobs that were almost but not quite complete. Both upper rooms in the larger building now have new floors and finally we have finished the roof!

Finished schist roof

(more…)

Stairs finished

Sunday, September 25th, 2011

Following on from the last post on the subject – and a bit overdue since they’ve been completed at least a couple of weeks now – we have finished the stairs on both sides of the building. This makes 3 sides of the building now protected from the weather by an extra overhang. All that remains now is to complete a lean-to roof along the back wall, dig a large drain into the bedrock behind it, and we should have a substantially watertight building … even without all the windows and doors.

Outside stairwell on schist dry stone building

(more…)

Floorless 2

Sunday, August 14th, 2011

As well as work on the outside of the larger building, we’ve also stripped out the floor in the left half of the building in preparation for reflooring and started cleaning and preserving the chestnut timbers. We stripped the right side of the building last November and it still hasn’t got its new floor yet … ah well … the best laid plans of mice and (wo)men …

In doing so the building revealed more of its life story: something we hadn’t been aware of until letting all this extra light in.

Back wall of larger building

(more…)

Stairs

Saturday, August 13th, 2011

After a break of the best part of 3 months, we’ve been able to start work on building renovations again. The first priority is to complete the roof of the larger building. The roof over the main body of the building itself is done, but we need to extend it either end of the building to cover the external staircases, and to butt a lean-to roof up to it along the back of the building before it’s finally finished.

Extending the roof area right round the house in this way will, aside from providing covered walkways, give all round protection to the walls from most direct weather action: a major consideration with dry-stone walls, especially ones that are going to be clay-pointed.

The larger building

(more…)

More on renovations

Sunday, May 8th, 2011

Progress. The balcony, patio area and log store outside the main building are now substantially finished.

It has been quite a transformation.

(more…)

Dinner time

Tuesday, May 3rd, 2011

We have been living on the quinta now for over a year with a severe lack of convivial eating furniture. Last year a slightly decrepit foldaway camping table and some slightly decrepit foldaway chairs did the job, but barely. 6 people to a meal meant there was only enough room on the table for the food. Plates on knees didn’t make for easy enjoyment of the fruits of our labour in the garden, and neither did the occasional chair collapse, so a workshop on lashings at Easter weekend’s Encontro Verde provided both inspiration and skills to remedy the situation.

A few days ago I went up into the woods to cut pine poles for the purpose with Valeri, our new WWOOFer, and today we started work.

Lashing poles to make tripods

Lashing 3 long poles together to make a tripod. The middle pole lies in the opposite direction to the outside pair.

(more…)